EISL B - summary costs
EISL B
£ million
Station 58
Airport walkway 6
Airport crossing 53
Newbridge - Ratho quadrupling 15
Rail junctions and viaducts 137
Road and tram bridges 55
Rail trackbed 20
Other civil works 4
Rail trackworks 50
Rail signalling and communications 25
Rail electrification 17
Land 35
Sub-total 474
Optimism bias (44%) 208
Total estimate 682
Less: savings from simultaneous construction -82
Reduced estimate 600

Table 3: EISL B summary of costs